It’s the moment you’ve been waiting for: our 2026 Grand Champions of Fusion have been chosen!
Congratulations to domestic winners JAKE DUHAIME and TYLER RISNER, along with international winners DIEGO VILLEGAS VILCHES (Chile), FERNANDO GUIJARRO (Mexico), and BRETT CARTON (Australia)!
JAKE DUHAIME






On this 10-inch waterline project in south Boston, Jake and his team fused 10″x10″x6″ tees for fire hydrants that, in all, consisted of roughly 1,300 feet of 10″ DIPS. The project had to be completed as quickly as possible because it was taking place in an active train yard.
The trench work, combined with the pipe’s weight, made the work a challenge, but Jake and the other fusion technicians completed the job in about two weeks.
TYLER RISNER






Tyler began installing underground HDPE piping on this dairy expansion project in July 2025. The project is a major expansion and remodel of an active dairy farm, with an anticipated completion date in summer 2027. Key additions include an 875′ x 675′ free-stall barn, multiple maternity barns, and a new state-of-the-art 120-cow GEA rotary milking parlor, which is scheduled to begin operation on September 1, 2026.
As of the time of Tyler’s submission, the project had utilized approximately 1,000 feet of 1″ IPS DR11, 4,000 feet of 2″ IPS DR11, 12,000 feet of 4″ IPS DR11, 1,800 feet of 6″ IPS DR11, 21,000 feet of 6″ IPS DR21, and 2,500 feet of 8″ IPS DR11 HDPE pipe. An additional contractor installed approximately 800 feet of 12″ DIPS DR21 pipe.
Multiple fusion methods and equipment have been used throughout the project, including the Pit Bull® 14 and TracStar® 28. Although Tyler’s company first began working with HDPE in April 2025, he was selected as the sole employee to learn and lead HDPE installation. While transitioning from 6″ to 8″ pipe presented new challenges, particularly when fusing 8″ tees with the TracStar 28, the experience has expanded my knowledge and skills. I also learned to overcome alignment challenges associated with long-sweep 90-degree fittings, achieving precise riser placement within 1/4 inch tolerance.
The largest challenge has been working on an operational dairy farm that cannot tolerate water interruptions. Because the farm milks 3,000 cows three times daily, shutdown windows are extremely limited, requiring new systems to be installed around existing infrastructure rather than replacing it outright. Once the expansion is complete, the facility will support 8,000 cows milked three times per day, allowing the old plumbing systems to be removed.
DIEGO VILLEGAS (CHILE)




Diego’s photos come from Chile, where he performed fusion work on a 12-inch, DR 7.4 acidified discharge line for a copper leach heap irrigation project. This job took place on a mine in Antofagasta.
FERNANDO GUIJARRO (MEXICO)

Fernando submitted this photo of a 9km pipeline that needed to be quickly fused for a mine in Sonora, Mexico. After seeing the Tritan® 560 at work, Fernando’s team knew the machine could help optimize both the operation cost and time required for fusion work.
The project engineers were so pleased with the results that they added more fused HDPE to their project plans.
BRETT CARTON (AUSTRALIA)



Brett’s submissions come from the Iron Bridge Magnetite Project, a large-diameter HDPE fusion job in the Pilbara region of Western Australia.
As part of the ongoing construction and expansion works at Iron Bridge, Brett’s team at PPS Water Group was brought into complete HDPE fusions throughout the operation, including plant infrastructure, pond installations, and port-side works. The project involved the installation of large-diameter HDPE piping used for mine process water, slurry handling, and associated water management systems.
The team utilized four McElroy TracStar® 900 fusion machines during the project. Having used McElroy equipment for more than 18 years, the team selected the TracStar 900 because of its mobility, productivity, and suitability for large-diameter mining applications. The machines’ self-propelled design proved particularly valuable when working around trenches and confined work areas.
The project also highlighted the importance of digital quality assurance. DataLogger® technology was utilized throughout the project as a contractual requirement, providing comprehensive weld records and full traceability of fusion parameters. The ability to document machine settings, fusion data, and operator information helped ensure quality compliance while providing long-term accountability for every joint installed.
The Iron Bridge development itself is unique in scale. In addition to the plant infrastructure and water management systems, the operation includes a 135 km concentrate pipeline connecting the mine to Port Hedland. PPS Water Group also assisted another contractor with welding portions of the HDPE liner pipe used within this pipeline system, supplying both personnel and additional TracStar 900 machines to support the work.
As we close out another fantastic Champions of Fusion contest year, we’d once again like to thank everyone who participated – whether you submitted a photo, discussed entries on our social media channels, or even encouraged those in your network to take part. Our mission – to improve the world through improved infrastructure – wouldn’t be possible without the tireless efforts of our “boots on the ground” technicians and operators.
Please continue to submit your jobsite photos and stories to our CHAMPIONS OF FUSION PORTAL. Entries received past June 15, 2026 will automatically be rolled into our 2027 contest, and we’ll begin promoting that through our various social media platforms in the near future.
If you weren’t selected this year, please continue to enter! A previous entry does not disqualify you from entering again, and while the competition is fierce for our grand prize winners we are proud to showcase all of our qualifying entries.
Again, congratulations to our winners, and to everyone who participated! Now let’s roll up our sleeves and get back to doing what we do best: making the world a better place, one fused joint at a time!

